Scope of Work: Property Repair
What a contractor will do, to what standard, by when, and for how much
Property and unit | [Address], Unit [number] |
|---|---|
Prepared by | [Name, company] |
Contractor | [Company name], license [number] |
Contractor contact | [Name, phone, email] |
Date | [Date] |
Write this before asking for prices, so every contractor bids on the same work. Anything not written here is not included.
1. Summary
[One or two sentences. For example: Repair water damage to the bathroom ceiling in Unit 4B after the leak from Unit 5B was fixed, and return the ceiling to its original finish.]
2. Work included
# | Task | Location | Quantity |
|---|---|---|---|
1 | [Remove and dispose of damaged drywall] | [Bathroom ceiling] | [About 40 sq ft] |
2 | [Install new moisture-resistant drywall, tape, and finish to match] | [Bathroom ceiling] | [About 40 sq ft] |
3 | [Prime and paint the full ceiling to match existing color] | [Bathroom] | [1 room] |
4 |
3. Not included
[Repairs to plumbing in Unit 5B (already complete)]
[Mold testing or remediation, if found; stop work and call us]
[Any work outside the bathroom]
4. Materials and finishes
Item | Specification | Supplied by |
|---|---|---|
[Drywall] | [1/2 in. moisture-resistant] | [Contractor] |
[Paint] | [Brand, color name and code, sheen] | [Contractor / Owner] |
5. Site rules
Working hours: [8:00 a.m. to 5:00 p.m., Monday to Friday]
The unit is occupied. We will give the tenant notice of entry; do not enter outside the scheduled window.
Built before 1978: [yes / no]. If yes and the work disturbs painted surfaces, the contractor uses an EPA lead-safe certified firm and lead-safe work practices.
If you find damage, mold, or other conditions not described here, stop that part of the work and send photos to [name] before going further.
Protect floors, fixtures, and belongings; remove debris and leave the area broom-clean every day.
Parking and access: [where to park, how to get keys]
6. Schedule
Start | [Date] |
|---|---|
Finish | [Date] |
Working days | [Number] |
7. Permits and inspections
[The contractor will get any permit the work needs and schedule the inspection / No permit is expected for this work.]
8. Price and payment
Price | [Fixed price of $___ / time and materials at $___ per hour plus materials, not to exceed $___] |
|---|---|
Payment | [Paid in full within [number] days of completion and acceptance] |
Changes | Any extra work must be approved in writing, with a price, before it starts. |
Lien waiver | With final payment, the contractor gives us a lien release for the amount paid and confirms that its suppliers and subcontractors have been paid. |
9. Completion
Walk through the finished work with [name] and fix anything on the resulting list.
Provide before and after photos and receipts for materials we pay for.
Warranty: [workmanship guaranteed for [period] from completion].
10. Insurance and license
Before work starts, the contractor gives us a current certificate of insurance [naming [company] as additional insured] and a license number we can check.
Name | Signature | Date | |
|---|---|---|---|
Owner or manager | [Name] | [Signature] | [Date] |
Contractor | [Name] | [Signature] | [Date] |