Claim to Requirement Map
Eleven claims, nine requirements, one scope cut
| Claim | Req | Status | Verdict | Surfaces |
|---|---|---|---|---|
| Inspect a unit with no signal at all | R1 | Complete | Clear | 3 |
| Mark the damage on the photograph itself | R2 | Complete | Clear | 3 |
| The renter signs on the device | R3 | Complete | Clear | 3 |
| Damage costs priced before the renter drives off | R4 | Cut at T-11 | Blocked | 4 |
| An end to disputed damage invoices | R4 R9 | Cut, partial | Blocked | 3 |
| The report reaches the renter before they leave | R6 | Email only | Narrow | 3 |
| Conflicts resolve themselves on reconnect | R5 | Complete | Clear | 2 |
| Every inspection in the fleet in one view | R7 | Complete | Clear | 3 |
| Scan the unit and the record loads | R8 | Complete | Clear | 2 |
| Charges post straight to the ledger | R9 | Read only | Blocked | 2 |
| Cuts inspection time in half | none | No requirement | Unsourced | 4 |
| 11 claims across 7 surfaces | 6 complete, 2 partial, 1 cut | 6 clear, 1 narrow, 3 blocked, 1 unsourced | 32 |
Four bad claims are thirteen sentences
The three blocked claims and the unsourced one appear thirteen times across six of the seven surfaces. Counting claims makes this a morning. Counting instances makes it a two-day job with six owners, which is the truth.
The gap that produced all of it
Messaging last edited on the Wednesday of week 8. Scope cut on the Monday of week 10. Fifteen days in which finished-looking copy was wrong and no review cycle would have caught it, because the review happened in week 9.
One surface was clean: the in-app notice, four claims, all clear. It was written in week 10 by an engineer looking at the running build.