River
Y CombinatorBacked by Y Combinator

For consultants in the first week of a project

Project Charter Template and Example

Nine sections for a client project, from measurable objectives to sponsor sign-off, each with its rules, plus a worked example and a one-page version.

Download (.docx)Free download. No account needed.
Example

Project charter: member onboarding redesign (example)

Kestrel Valley Credit Union · Sponsor: Maria Okafor, COO

Purpose
Cut the nine-day wait for a usable account: redesign account opening, pilot it at two branches, recommend a rollout.
Objectives
From 9 to 3 business days to a usable account, and online drop-off from 31% to under 20%, by 5 Feb.
Out of scope
Business accounts, core system changes, and rollout beyond the two pilot branches.
Budget
$118,000 fixed, as in the SOW. The vendor's estimate for online form changes is due 20 Nov.
Sign-off
Sponsor, client project lead and engagement lead, 6 Nov.

What you'll get

A charter for client projects, with rules, a worked example and a one-pager

  • Nine sections, each with its rules, from purpose to sign-off
  • A one-page version for short projects and pilots
  • A complete example charter, annotated section by section

Before and after

Your SOW summary in. A first-draft charter out.

What you paste (example)

SOW signed with Kestrel Valley Credit Union. Redesign member onboarding, pilot at 2 branches, 2 Nov to end of Feb, $118k fixed. Sponsor Maria Okafor, COO. New accounts take 9 days today. Need data from IT. Compliance must approve any change to ID checks.

Your first draft (excerpt)

1. Purpose: New accounts at Kestrel Valley take nine days to open today. This project will redesign account opening, pilot it at two branches and recommend whether to roll it out. 2. Objectives: Cut the time to open a new account from 9 days to [target] by [date]. 6. Stakeholders and roles: Maria Okafor, COO, is the sponsor. [Compliance approver] approves changes to identity checks. [IT data owner] provides the data by [date]. 8. Budget: Consulting fees are $118,000, fixed. To confirm with the client: Who in IT provides the data, and by when? Who in compliance signs off changes to identity checks?

Facts your notes don't give stay in brackets, and each one becomes a question for the sponsor.

Why it works

What is a project charter, and what goes in it?

This project charter template sets out why a client project exists, what it must achieve and who decides, so the sponsor can approve it before the main work starts. A project charter formally authorizes a project, and the sponsor approves it, in the words of California's project management framework. PMI's definition, quoted in Cleveland State University's open textbook, adds that it gives the project manager authority to apply organizational resources.

The template has nine sections, and each one opens with its rules. You write three to five objectives, each with a measure, today's figure, a target, a date and a source. In scope carries numbers, and out of scope names the client's next likely ask. Every deliverable has one client person who accepts it, and every milestone shows what it depends on from the client. On consulting work the SOW is the contract and the charter is how both teams run the project, so it never widens the SOW.

A second doc is a one-page version for short projects and pilots. A third is a complete charter for an invented credit union, annotated section by section. Download all three as Word files with no account, or open them in River and paste your SOW summary or kickoff notes for a first draft. If the SOW isn't written yet, start with the SOW generator. Then settle who does what with the RACI matrix template, and map the people around the project with the stakeholder analysis template.

What lands in your doc

What's inside the project charter template

  • Nine sections, in order
    Purpose, objectives, scope, deliverables, milestones, roles, risks and assumptions, budget, and sign-off.
  • Rules in every section
    Each section opens with what goes in it and what stays out, plus examples where they help.
  • Measurable objectives
    A table for three to five objectives, each with a measure, its source, today's figure, a target and a date.
  • Who decides what
    Roles from both sides, one sponsor, who accepts each deliverable and how changes get approved.
  • A one-page version
    The same nine headings on a single page, for short projects, pilots and proofs of concept.
  • An annotated example
    A complete charter for an invented credit union project, with a note on why each section works.

How it works

From SOW to signed charter

  1. Open the template

    Click Edit with AI. The charter, the one-page version and the example open in River.

  2. Paste your notes

    Optional. Paste your SOW summary or kickoff notes, and River drafts every section from them.

  3. Fill the gaps

    Every fact your notes don't give stays in brackets, listed as questions to ask the sponsor.

  4. Sign it in week one

    Run the checklist, walk the sponsor through the charter, and get three signatures before the main work starts.

Questions consultants ask

Common questions

What is a project charter?

A project charter is a short document that authorizes a project and records why it exists, what it must achieve, what's in and out of scope, and who decides. The sponsor approves it before the main work starts. On a client project, it turns the signed SOW into the plan both teams work to.

What should a project charter include?

Nine parts: purpose, three to five measurable objectives, scope in and out, deliverables, milestones, stakeholders and roles, risks, assumptions and constraints, budget, and sign-off. The longer list in Cleveland State University's open textbook adds headings such as high-level requirements and exit criteria. On client work, the SOW usually covers those.

What's the difference between a project charter and a statement of work?

The statement of work is the contract: what you deliver, how it's accepted and what the client pays. The charter is how both teams run the project: why it matters, how success is measured, who decides and what could go wrong. It repeats the SOW and never changes it. Our statement of work template covers the contract side.

Who signs a project charter?

The sponsor approves it. California's project management framework gives the sponsor that approval, and other initiation work waits for it. On consulting work, have the client project lead and your engagement lead sign the same version, so all three agree on scope and roles. After that, change it only through a change request.

How long should a project charter be?

Two to four pages for most client projects, or one page for a short project or a pilot. California's framework keeps a separate mini charter for small, low-complexity projects, pilots and proofs of concept. This template includes a one-page version for the same reason. If a section of the one-pager runs past three lines, switch to the full template.

How do I write measurable project objectives?

Write a result, not an activity. Then give it a measure, today's figure, a target, a date and where the figure comes from. "Cut the time to a usable account from 9 to 3 business days by 5 February" works, and "improve onboarding" doesn't. Measure what the project can reach by its end, and hand longer-term targets to a named client owner.

Can I paste client details from my SOW?

Yes. Whatever you paste stays in your own River space unless you choose to share it. Under River's privacy policy, it isn't used to train AI models, and River's AI providers have agreed with River not to train on it either. Check your contract with the client first if it limits where project details can go.

Agree the project before the work starts

Open the charter with every section and rule in place, or paste your SOW summary or kickoff notes for a first draft with the gaps marked.