Critical path read, 8 September
Ostara Logistics Group, $284,000, signature target 30 September
| Steps in the plan | 17, after four collapsed rows were taken apart |
| On the critical path | 6 |
| Days lost so far | 35, across two steps, with the signature date unmoved |
| Deadline behind the deadline | 26 September, when Ostara's capital budget closes |
1. The path, backwards from signature
| Step | Side | Days it takes | Started |
|---|---|---|---|
| Accessibility conformance report | Us | 15 | No |
| Security review sign-off | Ostara | 19 | Blocked |
| Requisition raised and approved | Ostara | 8 | No |
| Redlines returned and resolved | Both | 26 | No, counsel back 15 Sep |
2. The arithmetic nobody had done
Sixty-eight days of remaining path against twenty-two days of calendar. The signature date moved three weeks ago; it just had not been written down anywhere.
3. The sentence
Tomas Ballard has to get the accessibility report booked for 9 September, or Hana Vance cannot sign off, the requisition cannot be raised, and Ostara's capital budget closes without us in it.
Five of the six steps on the path came out of a single row originally labelled Procurement and security. Nothing on that row had an owner with a name.