Grant Closeout Checklist Template
Three documents and three sheets that compute the reporting deadline and the record retention clock from two different dates, not one shared guess.
Free download · No account needed
Most grant closeout checklists stop at the same point: file the final reports, liquidate the last obligations, and treat the award as finished. 2 CFR 200.344(b)-(c) does require exactly that, no later than 120 calendar days after the period of performance ends for a direct award, 90 days for a subaward reporting to its own pass-through entity under the terms that award set. What that deadline does not do is close the file. Obligations survive it, and they start running on dates the checklist never names.
2 CFR 200.334 sets general record retention at three years, but the clock starts on the date the final financial report was actually submitted, not on the award's own end date, and the two are rarely the same day. Property acquired with the award runs a separate, later clock. 2 CFR 200.313(c)(1) lets the organization keep using it for as long as it is needed. Its own three-year retention period does not begin until that specific item is finally disposed of, however many years after the award closed that turns out to be.
Ridgeline Family Services closed a three-year federal award with a period of performance ending 2026-06-30 and filed its final report on 2026-10-05, 23 days ahead of the 120-day deadline. Retaining records for three years from the award's own end date instead of from that actual submission date misses the correct end by 97 days. A passenger van bought with the award stayed in active use for more than two years before finally being sold, on 2028-09-12, which starts its own retention clock more than 23 months after the general records clock has already closed.
What is in the pack
Final Report
The programmatic narrative against the award's original objectives for its whole period of performance, not just the last reporting period in isolation.
Closeout Certification
The signed record that every report was filed, every obligation liquidated, and any refund actually paid, dated rather than assumed.
Property Disposition Note
What happens to equipment once it is no longer needed, including the SF-428 report some awarding agencies require and others do not.
Closeout Requirement Checklist by Award
One row per award with its own 120 or 90-day deadline, tracked against the obligations already logged for it.
Final Reconciliation
Total funds drawn against total allowable costs incurred, with any refund owed stated as a signed number and a paid date next to it.
Retention Schedule
Every retention obligation on its own row, computed from its own real trigger date rather than one shared assumption about when the award ended.
How it works
- 1
Send the award terms and property records
Every award reaching the end of its period of performance, the final financial records, and a list of any equipment bought with it and whether it is still active.
- 2
Build the closeout checklist
The 120 or 90-day deadline computed for each award from its own end date, and whether the reporting calendar already tracked toward it.
- 3
Reconcile the final financial report
Total funds drawn against total allowable costs, with any refund identified, paid and dated on the same record rather than left open.
- 4
Compute every retention clock separately
General records from the submission date, property records from disposal, each with its own end date rather than one shared guess.
Frequently asked questions
Does closing an award out end our recordkeeping obligations?
No. Filing the final reports and liquidating obligations within the deadline closes the award. General records still have to be retained for three years from the date the final financial report was actually submitted. Property acquired with the award runs its own, later clock that only starts once that item is disposed of.
What is the actual deadline for the final reports?
120 calendar days after the period of performance ends for a direct award, or 90 days for a subaward reporting to its pass-through entity, per 2 CFR 200.344(b)-(c). Failing to comply, including missing that deadline, gets recorded in SAM.gov, a record other funders can see before deciding whether to fund this organization again.
When does the retention clock for equipment actually start?
Not on the award's end date. 2 CFR 200.313(c)(1) lets the organization keep using equipment bought with the award for as long as it is needed. The three-year retention period for its records only begins once that specific item is finally disposed of, which can land years after the award itself closed.
What do we owe the funder when we sell equipment bought with the award?
Above $10,000 in current fair market value, the Federal agency's entitlement is its original percentage contribution multiplied by the gross sale price, not a net figure computed first. In the worked example, a $16,000 sale at a 75% federal share comes to $12,000, reduced by a $1,000 selling-expense allowance the agency permitted, for $11,000 actually owed.
Is this the same as the SF-425 federal financial report?
No. The SF-425 reports one award for one period while the award is still active, built from accounting fields like cash on hand and unliquidated obligations. This pack's Final Reconciliation compares total funds drawn against total costs incurred once the award has stopped running entirely, which is a later and simpler question.
Does this replace the single audit?
No. Single audit fieldwork tests whether costs charged across every federal award an organization holds were allowable and properly supported. This pack decides when one specific award's own reports, property and records are actually finished, which is a narrower and later question than an audit answers.
What if the indirect cost rate was not finalized when the final report was due?
File the final financial report anyway, using the current or most recently negotiated rate, since the 120-day deadline itself does not move. A revised final report is then owed once the rate is finalized, and the allocation plan behind that rate is what the revision actually reconciles against.
Find out which of your obligations actually survive closeout
Send the award terms, the final financial records and your property list. The first thing back is every retention clock computed from its own real trigger date.
Build my closeout schedule