Assignment Register, sorted by slack
The Halstead Ledger reading its Q2 feature schedule on Monday 6 April 2026. 41 commissioned features, 48 slots, 12 weeks, an eight stage chain. Latest start is the last day the current stage could begin and still make the slot. The ten worst rows, then the four the desk looks at next.
| ID | Story | Slot | Stage now | Latest start | Slack | Chain left | Verdict |
|---|---|---|---|---|---|---|---|
| A-06 | Downtown parking garage debt | wk 2 | Reporting | 2026-03-02 | -25d | 35d | Impossible |
| A-01 | Emergency housing contract renewals | wk 1 | First draft | 2026-03-20 | -11d | 16d | Impossible |
| A-26 | Rental inspection failures | wk 5 | Reporting | 2026-03-23 | -10d | 35d | Impossible |
| A-16 | Farmworker heat rules | wk 4 | Reporting | 2026-03-25 | -8d | 28d | Impossible |
| A-19 | Bridge inspection deferrals | wk 4 | Reporting | 2026-03-25 | -8d | 28d | Impossible |
| A-05 | Nursing home inspection backlog | wk 2 | First draft | 2026-03-27 | -6d | 16d | Impossible |
| A-02 | County transit fare rise | wk 1 | Developmental edit | 2026-03-30 | -5d | 10d | Impossible |
| A-04 | Water board rate settlement | wk 1 | Developmental edit | 2026-03-30 | -5d | 10d | Impossible |
| A-07 | Sheriff overtime spending | wk 2 | First draft | 2026-03-30 | -5d | 15d | Impossible |
| A-03 | School bus driver shortage | wk 1 | Revision | 2026-04-01 | -3d | 8d | Impossible |
| A-28 | Community college transfers | wk 6 | Reporting | 2026-04-06 | 0d | 30d | Starts today or never |
| A-08 | Charter school enrolment audit | wk 2 | Revision | 2026-04-08 | +2d | 8d | At risk |
| A-14 | Library branch closures | wk 3 | Developmental edit | 2026-04-13 | +5d | 10d | At risk |
| A-11 | Airport concession contracts | wk 3 | Copyedit | 2026-04-23 | +13d | 2d | On track |
A-06 is the shape of the whole problem. It is a week two story, so nothing about its row looks wrong on a date grid and nobody has flagged it. Its remaining chain needs 35 working days and there are 10 before the slot, which puts it 25 days past the point of no return on the morning the calendar was read. A-33 fails the same way out in week seven: 37 days of chain against 35 available.