Consulting Programme Management Template

Four documents and three sheets that check every cross-workstream handoff against the providing workstream's own plan, not the receiver's assumption.

Free download  ·  No account needed

Interlock Note  ·  Marrow Bridge Consulting  ·  Thoreston Industrial Supply Co. ERP replacement  ·  10 Feb 2027

One dependency, reconciled against its provider's own plan, not the receiver's assumption

Chain stepPlannedForecastFloat to 30 Apr
Data cleansed2 Mar19 Mar42d
Integration testing23 Mar9 Apr21d
UAT complete6 Apr23 Apr7d
Controls sign-off13 Apr30 Apr0d
Go-live16 Apr5 May-5d

Data Migration's own plan showed this 17-day gap on 10 February, 20 days before Systems Integration's own plan would have discovered it on 2 March with nothing to show for it.

Fourteen days of original slack, gone, and five more borrowed, on a chain where no internal handoff carried float of its own.

Search programme management template consulting and the field has a real, settled answer. A dependency matrix shows the shape of the network, a dependency log carries a needed-by and committed-by date with an owner on each side, and a critical-path roll-up sequences the whole thing against the final date. That is genuinely good practice, and most of the leading templates in the category ship some version of all three. What none of them checks is where the committed-by date in that log actually comes from.

Read closely, the owner named on the providing side is usually whoever answered the request, not someone with visibility into that workstream's real schedule. The committed-by date next to their name is therefore often just the receiving workstream's own hope, typed into a column that looks like verification. This pack's register reads that date somewhere else: the providing workstream's own, independently maintained task register, for the specific task that produces the thing. Both numbers already exist in two documents. Nobody had opened them side by side.

Marrow Bridge Consulting's ERP programme for Thoreston Industrial Supply Co. sequences four workstreams against one date that cannot move: the legacy platform's vendor support expires 30 April 2027, after which, as NIST's own patch-management guide puts it, a fix "will never be released because the software is at end-of-life." On 10 February, Data Migration's own plan showed its data-cleansing task landing 17 days after Systems Integration's own plan had assumed, caught 20 days before that gap would otherwise have surfaced on its own.

One broken handoff out of six, and it is the one that sits on the path to go-live

The Dependency Register, the Milestone Interlock, and the Critical Path.

Cross-workstream Dependency Register

Six handoffs between four workstreams. Every provider date is read from that workstream's own plan, never asserted by the receiver.

IDProvider → ReceiverReceiver NeedsProvider CommitsStatus
D-01Controls → Data Migration26 Jan22 JanOn Track
D-02Training → Data Migration2 Feb2 FebOn Track
D-03Data Migration → Integration2 Mar19 MarBroken, +17d
D-04Integration → Training15 Feb12 FebOn Track
D-05Training → Controls6 Apr6 AprNot yet due
D-06Data Migration → Controls30 Mar30 MarOn Track

One Broken row out of six. D-06 shares its provider with D-03 and is unaffected, because the delay is scoped to one specific task inside Data Migration, not the whole workstream.

The Cascade

Four workstreams, one sequential chain, zero float at any internal handoff.

MilestonePlannedForecastSlip
Data cleansed2 Mar19 Mar+17d
Integration testing complete23 Mar9 Apr+17d
UAT complete6 Apr23 Apr+17d
Controls sign-off13 Apr30 Apr+17d
Go-live16 Apr5 May+19d

Seventeen days added at the source are still seventeen days four handoffs later. Nothing between these milestones was built with its own buffer, so nothing absorbs the slip until it reaches the one buffer the whole programme has.

Critical Path

Float remaining to the 30 April hard deadline, before and after the D-03 finding.

MilestoneFloat, PlannedFloat, Forecast
Data cleansed59d42d
Integration testing complete38d21d
UAT complete24d7d
Controls sign-off17d0d
Go-live14d-5d

Fourteen days of slack planned, five days short once the slip is applied. Found on 10 February, that is 20 days before 2 March, the date Systems Integration's own plan would otherwise have discovered the gap with nothing to test.

What's in the pack

01

Programme Charter

Names the four workstreams and their owners, and the one external date, a vendor's end of support, the whole sequence is planned against.

02

Cross-workstream Dependency Register

Every handoff between workstreams, with the receiver's assumed date and the provider's own committed date sourced into the same row.

03

Milestone Interlock

The same network laid out as a sequence, showing what each workstream's milestone feeds into next, and its current status.

04

Critical Path

Float remaining to the hard deadline at every step, so a slip's real cost is visible before it reaches the final date.

05

Dependency Network Map

Which of the network's edges actually sit on the path to go-live, and which only matter inside one workstream's own schedule.

06

Interlock Note

The written brief a broken dependency produces: the finding, the cascade in days, and what the reconciliation bought in warning time.

07

Escalation Procedure

What happens the moment a dependency is found broken, and the two thresholds that send it to the steering committee rather than the next review.

How it works

  1. 1

    Open in River, or take it blank

    Edit with AI installs the pack as a private Space and starts the reconciliation. Download gives you the Word documents and CSV sheets free, no account.

  2. 2

    Send every workstream's own plan

    Not a rolled-up programme summary: each workstream's actual task register, so a provider's real committed date can be read from it directly.

  3. 3

    Get both dates in the same row

    The receiver's assumption and the provider's own commitment, side by side, so a gap is visible the moment it exists rather than the day it comes due.

  4. 4

    Trace anything broken to the deadline

    A variance gets carried step by step to the programme's actual external date, with the float remaining stated in days at every stage.

Frequently asked questions

Is this programme management template free?

Yes. Download gives you the whole pack with no account and no email: four Word documents and three CSV sheets. Edit with AI creates a free account, installs the same pack as a private Space, and reconciles your own workstreams' plans against each other.

What format are the downloaded files?

Word (.docx) for the four documents and CSV (.csv) for the three sheets, zipped together. Everything opens natively in Word, Pages, Google Docs, Excel, Numbers and Sheets. Add ?format=pdf to the download URL for the documents as PDFs.

How is this different from a standard dependency log or RAID log?

Most dependency logs name an owner on each side and a committed-by date, then trust whoever filled the row in. This pack's committed-by date is read directly from the providing workstream's own task register for the specific task involved, never typed in by the receiving side or a coordinator confirming a conversation happened.

What counts as a dependency being Broken versus At Risk?

Broken means the providing workstream's own plan, sourced directly, shows a later date than the receiving workstream assumed: a root cause. At Risk means a milestone's own forecast moved because something upstream of it broke, even though its own workstream did nothing wrong. The distinction decides who owns fixing it.

How is this different from the consulting workplan and resource tracker?

That pack tracks one workstream's own tasks against its own fee. This one starts where a single workstream's visibility ends: the handoffs between workstreams, where one side's plan can look fine in isolation while quietly disagreeing with what another workstream assumes about it.

Does this replace the steering committee's decision queue?

No. That pack runs the recurring meeting where a programme-level decision actually gets made. This one is what feeds it a finding worth deciding: a broken dependency, traced to its cost in days against the real deadline, with a specific ask attached rather than a status update.

Find the handoff nobody cross-checked

Take the Word documents and CSV sheets blank, or send River every workstream's own plan and get the reconciled register back.

Edit with AI